Project finance is a way of funding a single, ring-fenced asset — a solar farm, a toll road, a processing plant, a data centre — where lenders are repaid from the cash the project itself generates. It differs from a corporate loan, where the lender looks mainly at the borrower's existing balance sheet and trading history.

The SPV structure

The sponsor sets up a special purpose vehicle (SPV) that owns the project and signs all its contracts. The SPV borrows the debt, and the sponsor contributes equity. Because the SPV holds nothing except the project, lenders can assess it in isolation. Loans are often described as non-recourse or limited-recourse: lenders rely on the project's assets and contracts rather than on a parent guarantee, although sponsors usually provide support during construction.

How lenders size the debt

Lenders build a financial model of the project's revenue, operating costs, taxes and maintenance over its life. The amount they will lend is driven by how comfortably the forecast cash flow covers each period's interest and principal — the debt service coverage ratio, or DSCR. Riskier revenue (for example merchant power prices) means a higher required DSCR and therefore less debt; contracted revenue from a creditworthy buyer supports more. Lenders also look at the loan life coverage ratio and gearing (the split between debt and equity).

Contracts make cash flow bankable

A project is financeable when its main risks are allocated to parties able to carry them. Typical contracts include an offtake or concession agreement (who buys the output and on what terms), an engineering, procurement and construction (EPC) contract with a fixed price and date, an operations and maintenance agreement, land and permit rights, and insurance. Gaps in these contracts are the most common reason a project is not yet ready for debt.

Phases: development, construction, operation

During development the sponsor funds studies, permits and contract negotiation with equity. Financial close is when the loan documents are signed and conditions precedent are met. Debt is then drawn in stages during construction against certified progress. Once the project is operating, repayments begin, often sculpted so that debt service tracks the expected cash flow profile.

What to prepare

A credible sponsor team and track record; a feasibility study or independent technical report; the financial model; draft or signed offtake, EPC and O&M contracts; permits and land rights; the proposed equity contribution; and a clear timetable to financial close. Our debt-sizing tool gives an indicative view of how much debt a cash-flow profile might support before you approach lenders.

Costs and fees

Project finance involves lender due diligence, legal documentation and arrangement costs, which are agreed in writing in a term sheet. Westford never asks for an upfront or refundable fee before funding, and any fees are deducted from the facility at drawdown under signed documents.

Figures are indicative and do not constitute advice or an offer of credit.

Ready to fund your next project?

Project Finance: USD 1,000,000–1,000,000,000, indicative term sheet with fees in writing.

≈ $19,566/month at 6.5% representative (illustrative).

Share this insight:LinkedInXWhatsAppEmail

Related insights

¿Listo para financiar su próximo hito?

Envíe una propuesta en línea. Un ejecutivo se pondrá en contacto con usted.